Changes Happening at the RAC

Posted: June 5, 2017 at 9:47 am, Last Updated: July 12, 2017 at 11:29 am

 

  • Resurfaced Linn and RAC Gym in June!
  • Converting two locker rooms into storage space for Club Sports and RHT
  • Creating spacious Multi-Use Room for RSO’s, Club Sports, Training, and Professional Development Activities
  • Updated spacing and layout of Cardio Equipment on first and second floor
  • Added new sleek and state of the art vending machine – Vengo!

 

Timeline of events:

 

May 8th 2017 to May 26th 2017 – RAC Gym and Linn Gym floors refinished

 

June 1st 2017 – Cage Gym will go offline and construction will start on a new wood floor as well as renovations to the cardio gallery to add in an extra classroom / activity space

 

August 1st 2017 to August 25th 2017 – Linn Gym will go offline so a new divider curtain can be installed.